Our contractor Beck continues to make great progress on the renovations, with the following due to take place in April:

APARTMENTS

With all the remaining apartments having been handed over to Beck in March, the renovations are in full swing! Many of the apartments have been stripped out and work has started on space reconfiguration and connection to the new water system.

LIFTS

This month sees Beck take possession of Lift 2 at 60 Park Lane. This is to facilitate the removal of the existing lift car. Beck will continue with piling for the lift shaft and foundation works to prepare for the installation of the new lifts.

GENERAL

55 and 60 Park Lane: Corridors

The removal of ceiling panels continues so that IT, air conditioning and the new water system can be connected.

55 Park Lane: East and west courtyards

Beck continues to work on the stairwell windows for the relocation of the air conditioning units. The additional scaffolding and hoist erected in the west courtyard in March will stay in place for the coming months to provide additional access to the upper floors.

60 Park Lane: Chimney stack

Demolition and removal of stack continues throughout April.