august update

Our contractor Beck is making good progress and this month will be focusing on:

Apartments
The renovation work in 55 and 60 Park Lane apartments is ramping up! We are decorating apartments on the 5th and 6th floors of 60 Park Lane, and on 9th floor of 55 Park Lane. Our example room is now ready; let us know if you would like to have a look at it and we shall show you around.

55 and 60 Park Lane corridors
The removal of ceiling panels to facilitate IT, AC and the new water system continues, as does the installation of services in the 60 Park Lane corridors.

New lifts