april update

Our contractor Beck is making good progress and will be focusing on the following this month:

Apartments
The first set of apartments in the renovation schedule is finished and following our quality checks more will be released over the coming weeks. 

55 and 60 Park Lane corridors
Ceilings are being reinstated and protection removed from corridors, ready to return to normal operating standards. The 60 Park Lane corridor is being decorated and the renovation of the feature staircase continues. Lights will be installed this month.  

Basement
The new 60 Park Lane plant room is now fully functional.

Lift-core
Lift installation by our contractor Kone continues. 

Disability Discrimination Act (DDA) works
The main structural works at 20 South Street have been completed. The new Portland stone has been installed and protected and will be rendered this month.