Our contractor Beck is making good progress and will be focusing on the following In March:

Apartments
Apartments are now being handed back to Hyde Park Residence team for snagging. This is a thorough quality assurance process to ensure the highest standards are met. 

55 and 60 Park Lane corridors
Corridor ceilings are being reinstated and décor protection being removed ready to return to normal operating conditions. The 60 Park Lane corridor upgrade is progressing well so decorations are ongoing with flooring arriving later in March. 

Basement
The new plant room commission is underway and we hope that 60 Park Lane will be online by the end of the month. 

55 and 60 Park Lane connection
Work to the new link corridor continues, with the new windows in production and expected to arrive on site in the coming weeks. 

Lift-core
Our lift contractor Kone is now on site and has started to build the new lift mechanism and cars. Specialist finishes will follow.

Disability Discrimination Act (DDA) works
The main structural works at 20 South Street have been completed. The new Portland stone build and render will start this month.