october update

The activities and developments outlined last month remain much the same for November. Our contractor Beck is making good progress and will be focusing on the following this month:

Apartments
All apartments are now under construction. The first set of apartments due for completion are being decorated and bathroom tiling work is being done. The new timber flooring is being laid. The completed electrical works are being tested ready for the lighting to be installed. Kitchens have arrived on site and are currently being installed. 

55 and 60 Park Lane corridors
60 Park Lane corridors have now all been stripped, and the new ceilings, electrics and decorations are under way.
The restoration of the 60 Park Lane staircase has begun, with decades of paintwork being removed to reveal the original art deco features. 

Basement
The new plant room installation is almost finished. The new infrastructure and equipment has been installed ready for set up. 

55 and 60 Park Lane connection
The corridor is now ready for the new connection to be made this month. 

Lift-core
The lift steelwork is progressing well, with floors installed and concreted up to the 4th floor. The new connection through to 60 Park Lane is complete on every floor and the new structural floors have been installed.