september update

Our contractor Beck is making good progress and in September will be focusing on:

Apartments
All apartments are now under renovation.
The first apartments due for completion are being decorated, tiled and new timber flooring is being laid. The electrical works are being tested and readied for the lighting installation.
New walls and ceilings are being fitted for the final apartments to be renovated in the project (to be completed March 2022).

55 and 60 Park Lane corridors
All new services are now installed at 60 Park Lane and Beck is plastering the new corridor ceilings. New air conditioning pipework and power supplies at 55 Park Lane are now installed.
The upper floors of the building will hopefully be back in use towards the end of September.

Basement
Our new plant room is being fitted out. The new walls will be rendered and the floor screed this month.

55 and 60 Park Lane connection
Beck is erecting the new link corridor steel so the new connection between the two buildings will begin shortly.

60 Park Lane lifts
The lift steelwork is progressing as planned and has reached the 2nd floor. New connections through to the 60 Park Lane corridors are complete and the new floor structures are being installed.